2666 Crosscreek

Before Gallery

3 beds 2 baths 1,650 sqft

Week 1 – Demolition

We had to open up the garage and knockdown some interior walls to make the living room and dining room flow better as an open concept floor plan. Updated cabinets, new counter tops and doors on the way.

Week 2 – Windows & Doors Installed

New storm windows and interior doors were installed. In addition to the insulating qualities, the storm windows allow for less outside noise.

Week 3 – Backyard Demo & Cabinets

Back room demo was completed including the fireplace. The backyard demo was also done and the grass leveled.

Week 4 – Painting…First Coat

The cabinet doors finally came in and the first coats of paint have been completed throughout the home.

Week 5 – Exterior Paint & Counters

The paint is complete and got the new counter tops installed. Fixing everything including the kitchen sink!

Week 6 – Floors & Carpet Installed

Carpet is finally complete and we were finalizing the rest of the flooring. For this project we choose to go with a lvp in the bathrooms and a high quality laminate in the common areas.

Week 7 – Lighting

Lighting fixtures are in as well as new lighting installed. The last of the paint touch-ups have been completed as well.

Week 8 – Last Touch-Ups

Everything went well. Just some final touch-ups before everything’s good to go.

Week 9 – Finished Product

Carport’s done, backyard’s done, rooms are done, everything’s all set!

After Gallery

A few bumps and bruises but overall we the new Owner purchased a new home she could be proud of and will hold up for many years to come! Checkout the final gallery!